List of completed & current projects with percentage of completion | |||||||
As of February 2017 | |||||||
S/N | Client | Project Description | Start | End | Contract Value | Percentage of Completion | Current Value/(Final) |
A. | Completed Projects | ||||||
1 | Abu Dhabi Municipality | O&MAUH AK/G Ww Collection, Treatment & Disposal System | 10-Aug-02 | 29-Feb-08 | 18,159,965.00 | 100% | 18,159,965.00 |
2 | Abu Dhabi Municipality | O&M SN, PS & TP WR1 Delma, Baaya Sila & Ghayati | 2-Aug-03 | 2-Aug-08 | 42,158,673.00 | 100% | 42,158,673.00 |
3 | Abu Dhabi Municipality | O&M WR 1Storm & Sewage Collection, P, T & Irrigation Reuse Systems | 9-Jun-05 | 28-Feb-08 | 50,754,038.00 | 100% | 50,754,038.00 |
4 | Abu Dhabi Municipality | O&M WR 1&2, AK/G & AA Remote Areas | 1-Mar-08 | 31-May-12 | 266,523,150.00 | 100% | 266,523,150.00 |
5 | Abu Dhabi Municipality | O&M AUH Island Irrigation Pumping Stations & Reservoirs | 10-Jul-04 | 31-Dec-14 | 40,992,887.94 | 100% | 40,992,887.94 |
6 | UAE Armed Forces, Command of Military Works | O&M of WR Area Camps & AA Camps | 13-Aug-08 | 12-Aug-10 | 5,000,000.00 | 100% | 5,000,000.00 |
7 | UAE Armed Forces, Command of Military Works | O&M of WR Area Camps & AA Camps | 24-Dec-09 | 23-Mar-12 | 5,000,000.00 | 100% | 5,000,000.00 |
8 | UAE Armed Forces, Command of Military Works | O&M WR & Al Ain Camps Maintenance of Sewage Networks | 24-May-12 | 23-May-14 | 4,000,000.00 | 100% | 4,000,000.00 |
9 | UAE Armed Forces, Command of Military Works | O&M Abu Dhabi & Zayed Military Camps Maintenance of Sewage Networks | 12-Sep-12 | 11-Mar-14 | 3,000,000.00 | 100% | 3,000,000.00 |
10 | Abu Dhabi Transmission & Dispatch Company (TRANSCO) | Overhauling of Control Valves Electro-Hydraulic Power Units | 18-Jun-12 | 12-Mar-13 | 490,000.00 | 100% | 490,000.00 |
11 | ED Zublin AG | Maintenance of Sewage Networks – Strategic Tunnel Enhancement Programme | 22-Apr-15 | 16-Feb-16 | 4,785,882.11 | 100% | 4,785,882.11 |
12 | ED Zublin AG | Maintenance of Sewage Networks – Strategic Tunnel Enhancement Programme | 1-Jul-15 | 31-Jul-16 | 9,823,882.11 | 100% | 9,823,882.11 |
13 | Hilal Bil Badi (HILALCO) | Sewer Line Isolation & Flow Control – AD Island | 8-Dec-15 | 31-May-16 | 3,302,851.20 | 100% | 3,302,851.20 |
14 | Bin Hafeez Gen. Cont. L.L.C | Sewer Line Isolation and Flow Control and Existing Sewer Manhole Refurbishiement Works – Improvement of Al Mafraq to Al Ghwaifat Border Post Highway Section |
31-May-14 | 30-Jun-16 | 1,063,971.00 | 100% | 1,063,971.00 |
15 | METITO | Rehabilitation of Pumping Stations in Abu Dhabi | 20-Oct-15 | 23-Aug-16 | 3,298,196.86 | 100% | 3,298,196.86 |
16 | Abu Dhabi Maintenance & Construction Co. (ADMAC ) | O-12099 Upgrade of 7/2 Pumping Stations | 26-Nov-15 | 25-Dec-16 | 2,080,182.00 | 100% | 2,080,182.00 |
17 | ATHENA J&P LLC | Sewer Line Isolation, Flow Control & Installation of Backdrop | 4-Jun-15 | 9-Oct-16 | 1,046,430.00 | 100% | 1,046,430.00 |
18 | Al Jaber L.E.G.T. Engineering & Contracting (ALEC) L.L.C | Supply, Operation and Maintenance of Diesel Pumps & Storm water line isolation works at the Memorial Park Project – Abu Dhabi | 1-Oct-16 | 21-Dec-16 | 872,090.00 | 100% | 872,090.00 |
Sub-Totals | 462,352,199.22 | 100% | 462,352,199.22 | ||||
B. | Current Projects | ||||||
S/N | Description | Project | Start | End | Contract Value | Percentage of Completion | Current Value/(Final) |
1 | ADSSC | Contract No. O-11025 – O&M Contract West of Abu Dhabi Emirate | 1-Jun-12 | 31-Mar-19 | 594,044,970.84 | 72% | 429,775,786.34 |
2 | UAE Armed Forces, Command of Military Works | CMW14000-FM039 Abu Dhabi & Zayed Military Areas | 5-Aug-14 | 31-May-17 | 4,000,000.00 | 90% | 3,603,720.00 |
3 | UAE Armed Forces, Command of Military Works | CMW14000-FM048 Al Ain & Northerm Emirates | 6-Aug-14 | 31-May-17 | 4,000,000.00 | 68% | 2,702,260.00 |
4 | ADWEA | G-14127 Startup,Commissioning and O&M of Waster Water Treatment Plant-ADWEA Housing Complex | 18-Feb-16 | 1,156,000.00 | 17% | 201,500.00 | |
5 | ADMAC | Flow Isolation & Over Pumping Works at PS 7/13 Shahama | 1-Sep-16 | 4,000,000.00 | 88% | 3,513,169.00 | |
6 | HLG Al Habtoor Leighton Cont. LLC. | Sewerage Works – Flow Isolation & Over Pumping Works at Sheikh Shakhbout Medical City Project | 22-Feb-17 | 328,420.00 | 80% | 262,736.00 | |
7 | Wade Adams Contracting L.L.C | Sewer Line Isolation, Flow Control & Installation of Backdrop | 5-Jun-16 | 30-Jun-16 | 175,668.00 | 41% | 71,198.00 |
Sub-Totals | 607,705,058.84 | 72% | 440,130,369.34 | ||||
Totals | 1,070,057,258.06 | 84% | 902,482,568.56 |